Why Invest in Baja Mining?

  • Raised over US$ 1 billion in 2010
  • Under construction - Commenced in November 2010
  • Copper Production 2013
  • Low cost & long life producer
  • Excellent federal, state and local support

Construction Highlights (Feb 2012)   

  • ICA Fluor selected as EPCM contractor
  • EPCM 70% complete
  • Engineering 92% complete
  • Procurement 84% complete
  • Construction 37% complete
  • 2,400 people currently working on the project
  • 1,009 local (43% of total workforce)
  • 406 from Baja region (17% of total workforce)
  • 13% Women
  • Committed 80% of total project costs
  • Spent US$ 603M (Mar 2012)
  • Poured 56% of total 72,000 m3concrete
  • Completed >5.8M m3 of earthworks
  • Commissioned 7.5MW of power for mining
  • Mine maintenance facility operational
  • First desalination plants operational
  • Progressed acid plant erection 
  • Completed 20% of marine terminal 
  • Completed 22% of tailing storage facility

Stock Chart

Baja Mining is listed on the Toronto Stock Exchange (BAJ:TSX) and belongs to the S&P/TSX Global Mining Index and the S&P/TSX Global Base Metals Index.

Key Financials  
Senior Debt 2 US$ 408M
   

 

Share Structure

Shares Outstanding 339,963,025
Options 26,587,500
Warrants 23,855,109
Fully Diluted Shares 391,030,634

 